Condition Assessment Municipality of Skagway Borough · Project 22003.00
Report Date: Nov 11, 2023 · DEED 2020/2023 Standards

Skagway K-12 School Facility Condition Survey & Capital Improvement Plan

A comprehensive engineering, architectural, and ADA accessibility audit of the 50,000 ft² 1983 campus—documenting code deficiencies, mechanical lifecycle exposure, and a $7.15 million capital modernization roadmap.

5-Year Capital Plan (Exec. Summary) $7,150,000 Recommended priority capital investment
Facility Footprint & Lot ~50,000 ft² 1983 core + 1,640 ft² 2022 kitchen on 280,000 ft² lot
Campus Population 142 / 13 K–12 students / teachers & administrative staff
DEED Cost Model Multiplier 3.16× Alaska Program Demand markup over base cost
Section 01 Background Context, Facility History & Spatial Layout
1563 Main Street, Skagway, AK 99840

A 1983 Schoolhouse Anchored by Incremental Upgrades

Located between 15th and 17th Avenue on Main Street in Skagway, Alaska, the Skagway K-12 School serves roughly 142 students and 13 teachers and administrative staff within an approximately 50,000 ft² building on a 280,000 ft² municipal lot. Originally constructed in 1983 across two phases, the facility remains largely original construction despite targeted roof, fire sprinkler, and culinary additions.

To manage aging infrastructure risk and qualify for State of Alaska Department of Education & Early Development (DEED) Capital Improvement Project (CIP) grants, the Municipality of Skagway Borough retained CRW Engineering Group, Inc. alongside architectural subconsultant Northwind Architects, LLC. On June 14–15, 2023, the team conducted a visual condition survey—supported by selective finish removals, staff interviews, and a full Matterport™ Pro2 3D colorized point-cloud scan—integrated with a separate May 4, 2023 Americans with Disabilities Act (ADA) consultation by Southeast Alaska Independent Living, Inc. (SAIL).

Construction & Renovation Chronology

1983
Original Two-Phase Build
~50,000 ft² cast-in-place concrete foundation, wood-clad rainscreen walls, pitched hip roof, and central HVAC mezzanines.
2004
Partial Roof Replacement
Granulated metal tile shingle system installed over the pitched hip roofs.
2010
Fire Sprinkler Upgrade
Automatic fire sprinkler system replacement, relaxing modern door fire-rating mandates.
2021
Standby Diesel Generator
Pad-mounted standby generator installed with an integral 660-gallon double-walled subbase diesel fuel tank.
2022
1,640 ft² Kitchen Addition
North-side commercial Kitchen (30), Home Ec (33), North Storage (13A), flat PVC roof, and partial remodel of Rms 9A/9B & Store 10.
2023
SAIL ADA & CRW Survey
May 4 ADA audit and June 14–15 multi-discipline survey with Matterport 3D point cloud; final report Nov 11, 2023.

Interactive Campus System & Deficiency Map

Select any building zone or site parcel to inspect documented findings & costs
Schematic Zone Guide (Not to Scale)
PLAYGROUND & GROUNDS Gravel paths, swings, site poles Civil-2 · $689k w/ markup BASEBALL FIELD & TENNIS Regrading, dugouts, gates, bike rack Civil-1 · $82k+ w/ markup 2022 KITCHEN ADDITION Rm 30/33, PVC roof, 2021 Gen. Good condition · ADA path fixes WOOD SHOP 24 & MEZZANINE 5 AHUs + 2 VAV Utilidors Open plenum violation (IMC 602.2.1) Dust collection (HLS · Mech-3) Mech-2 & Elec-1 Focal Zone CLASSROOMS, LAB & LIBRARY Rms 9A/B, 29, 204, 219–20, 301–16 Underlit (<10 fc), no egress lighting Casework, VAVs, ACT bracing, F.E. Elec-1 · Arch-3 · Mech-1/2 GYM, LOCKERS & MEZZ. AHU-6 & AHU-7 (noisy/drafts) Cracked ceramic tile, felt walls ADA benches, flush, 60" circles Mech-2 · Arch-1/3 · Misc BOILER 26, JANITOR 21 & CHASE CSD-1 E-stops, water heater T&P/tank Panel "CP" NEC clearance violation South brick chase missing 1-hr firestop Mech-1 · Elec-2 · Arch-5 MPR 11, STAGE 7 & 10B Stage vinyl & 60"x60" ramp landing Restroom ADA & urinal platform Old Kitchen 10B hood & GFCI Arch-1 · Mech-2 · Misc MAIN ENTRY & PARKING 1,100 SF entry wood deck trip hazard Sidewalks, curbs, ADA parking Paving & curb-cut striping Civil-1 · $1.42M+ w/ markup
Section 02 Evaluation Criteria, Cost Model & Technical Alternatives
DEED 2020 Survey Guide & 2023 Cost Model

How Deficiencies Are Ranked, Priced, and Scoped

Each building system was evaluated by discipline engineers against two dimensions: estimated remaining useful life (RUL) on a 1–5 condition scale, and priority classification driven by failure consequence and code compliance. All ADA deficiencies from SAIL’s consultation and all life-safety hazards receive the highest urgency.

Priority Tiers (Section 3.2)

HLS Health, Life & Safety: Immediate replacement or mitigation recommended. Covers egress lighting, NEC clearances, dust collection, asbestos testing, fire extinguishers, and all ADA violations.
<5 yrs Near-Term Replacement: Systems past or nearing end of useful life, failing valves, AHU/VAV replacements, return-air ducting, DDC controls, and paving.
5–15 yrs Medium-Term Capital: Window IGU replacements, half of exterior finish carpentry, ACT seismic bracing, upper casework, stair deflection stiffening, and dugout repairs.
>15 yrs Long-Term / Good Condition: Recently replaced interior carpet tile (20 yr), 2022 kitchen sheet vinyl (20 yr), PVC flat roof, and 2021 standby diesel generator.

DEED 2023 Alaska Cost Model Multiplier

Across Attachment A, raw construction estimates (Cost without markups) are scaled by a consistent 3.1629× DEED Program Demand factor to reflect design, administration, contingency, and remote Southeast Alaska construction logistics. Test any construction scope below:

Base Construction
$100,000
Markups & Soft Costs (+216.3%)
$216,290
DEED Total Project Cost
$316,290

Documented Engineering & Execution Alternatives

Scope / Component Option A (Recommended / Preferred) Option B (Alternative Considered) Decision Criteria & Context
Low-Complexity Works
Misc Group (<5 yrs / HLS)
Execute via Skagway/School maintenance staff or local general contractors without full engineering plans. Bundle into formal engineered bid packages with full design drawings and specifications. Saves design overhead on items like labeling breakers, GFCI swaps, door closer adjustments, and clearing 36" corridors.
Janitor Rm 21 Panel "CP"
Item 82 · Elec-2
Rotate panel 180° in place so it opens directly into the adjacent hallway. Move panel to a new location and repurpose existing enclosure as a terminal junction box. Water and fire riser pipes obstruct the required 3-ft front working clearance (2020 NEC / NFPA 70).
Main Entry Wood Deck
Item 91 · Civil-1 (1,100 SF)
Demolish painted 2x wood deck and replace with poured concrete flatwork. Replace with a furred composite wood decking system matching grade transitions. Surrounding flatwork created non-compliant ADA threshold offsets and severe trip hazards.
Window Replacement
Item 22 · Arch-6
Fiberglass-clad wood-framed windows with high-performance low-e IGUs. All-fiberglass framed windows with high-performance low-e IGUs. Existing IGUs fail 2021 IECC Climate Zone 6 thermal target (U.3) and face 5-yr coating/seal RUL.
Exterior Finish Carpentry
Item 20 · Arch-6
Replace the ~50% deteriorated trim with improved venting & drainage detailing. Replace 100% of finish carpentry simultaneously if original wood-clad rainscreen is replaced. Half of existing trim remains in good condition requiring only periodic repainting.
Old Kitchen 10B Receptacles
Item 87 · Misc
Convert all room receptacles to GFCI if food preparation continues. Convert only receptacles within 6 ft of sink bowl top edge if food prep ceases. NEC 406.12 / sink-proximity protection scaled to actual operational use.
Section 03 Technical Specifications, Existing Conditions & Code Violations
5 Engineering Disciplines

System-by-System Condition Assessment

While the 1983 structural frame and cast-in-place concrete foundations remain sound, mechanical ventilation, interior lighting, plumbing isolation valves, and exterior envelope detailing carry acute code and lifecycle exposure.

01

Mechanical, HVAC & Plumbing

Ventilation: Wood Shop mezzanine (5 AHUs, 2 VAV utilidors) and Gym mezzanine (2 AHUs) operate as unrated return-air plenums (2021 IMC Sec. 602.2.1 violation), pulling wood shop air into school circulation. AHU-1, 2, 6, 7 and VAVs are past useful life; pneumatic controls need DDC upgrade.

Plumbing & Heating: 250-gal oil-fired water heater lacks cold-line expansion tank (UPC 608.3) and has undersized T&P valve (UPC 504.6). DHW recirculation pump is non-functional due to non-seating gate valves. Boiler Rm 26 lacks ASME CSD-1 emergency shutdown buttons.

Highest Capital Share · Mech-1/2/3
02

Architectural & Enclosure

Envelope: Original 1983 semi-vented cedar rainscreen uses untreated horizontal furring that traps moisture at base; UV-exposed cedar resists repainting. South mech chase unvented brick veneer lacks 1-hr firestopping at flue penetration (requires 3-sided rebuild). Soffits lack 316 SS screens.

Interiors: Carpet (20 yr) & 2022 kitchen vinyl (20 yr) are good; locker ceramic tile is failed (Condition Rank 1, 0 yr RUL, potential asbestos mastic). Portable door-securing devices violate NFPA 101; classrooms lack 2:A:20:B:C extinguishers (IBC 906.1); ACT grids need ASTM E580 seismic bracing.

Envelope & Life Safety · Arch-1–6
03

Electrical & Lighting

Lighting: Classrooms/offices are severely underlit (10 fc min; bathrooms <5 fc), and no building space has sufficient emergency egress lighting. Recommend swapping 2'×4' troffers for evenly spaced 2'×2' LEDs on dual circuits, plus 2 playground/parking light poles.

Power & Clearances: Panel "CP" (Janitor 21) and Boiler Rm 26 disconnects violate NEC 3-ft clearances. Wood Shop 24 needs dust-cover receptacles and central E-stop. Fuel oil/propane piping requires grounding; Nurse & Preschool rooms require NEC 517.13 review.

Life Safety Priority · Elec-1/2
04

Civil & Site Infrastructure

Circulation & Paving: Deteriorated asphalt driveway, sidewalks, and curbs force accessible paths behind parked cars and across active traffic lanes. Requires full sidewalk/curb rebuild, ramped curb cuts, accessible parking striping, and 1,100 SF entry deck replacement.

Recreation & Utilities: Regrade uneven baseball field; repair dugout benches/fascia; replace wooden fence post, fix latch gaps, and replace inoperable playground rolling gate. Install dedicated propane pad separated from 2021 generator.

Site Access · Civil-1/2
05

Structural Condition

Substructure & Superstructure: Overall structural assessment found no major systemic defects in the cast-in-place concrete foundations.

Targeted Repairs: Damaged exterior stem-wall insulation where coverings were removed, plus excessive deflection at the interior steel stair landing requiring welded/bolted steel angle stiffeners under the grating (Item 122, $15,815 w/ markup).

Generally Sound · Item 122
06

2022 Kitchen Equipment Spec

The new commercial kitchen (Rm 30) and standby generator are in good condition, housing:

  • 2× Garland MCO-GS-10S 60,000 Btu/hr propane convection ovens
  • Pitco single-vat floor-mounted propane deep fryer
  • Garland 9-burner gas range & Cleveland KEL25T 25-gal steam kettle
  • Streivor WCLC 1365722.5 Class I exhaust hood (verify Class K F.E.)
New 2021–2022 Assets

Building Code & Standard Deficiency Register

Filter documented code violations across IBC, IMC, NEC, UPC, NFPA, and ASHRAE
Section 04 Americans with Disabilities Act Consultation (Attachment B)
Assessed May 4, 2023 by SAIL

Four Pillars of ADA Remediation Across Campus

Evaluated independently by Southeast Alaska Independent Living, Inc. (SAIL) using the 2010 ADA Standards for Accessible Design and 2014 Checklist for Existing Facilities, every ADA item is elevated to HLS priority and integrated into Phase 1 project groupings. Two commercial kitchen items (Items 93 & 94) were already resolved prior to the November 2023 final report.

ADA Pillar 01 Routes & Doors

Hallways, Doorways & Pedestrian Travel

  • Stage/Music Ramp Landing (Item 110): Modify top ramp landing and door landing to meet 60"×60" minimum ($158,145 w/ markup, Arch-1) and repair handrail (Item 109, $22,140).
  • Door Opening Force (Item 111): Adjust closers on 7+ primary doors (stage/music, locker rooms, gym, laundry, library, student kitchen) to ≤5 lb pull force ($0, Misc).
  • Door Clearances (Items 112–113): Widen 28" door to 32" min; add 18" pull-side maneuvering clearance at Girls Restroom near stage ($3,795).
  • 36" Clear Corridors & 60" Turns (Items 95, 99, 102, 120): Clear storage/gym equipment in Mail Room, Rms 216/316, Commercial Kitchen, Gym Laundry, and free-weight area.
ADA Pillar 02 Heights & Casework

Usable Surfaces, Fixtures & Reach Ranges

  • Classroom Base Casework (Item 38): Replace lower casework with ADA-compliant 28"–34" height plastic-laminate cabinets ($772,646 w/ markup, Arch-3).
  • Dispensers & Controls (Item 97): Lower paper towel and toilet tissue outlets to ≤48" max height and ≥2" above grab bars across 5 restrooms.
  • Drinking Fountain & Appliances (Items 100, 116): Lower library water fountain ($6,326, Arch-1); replace Teacher’s Lounge refrigerator with bottom-freezer drawer model ($316).
  • Already Resolved (Items 93–94): Commercial kitchen 11"–25" knee depth under sink and storage box relocation marked fixed as of final report.
ADA Pillar 03 Restrooms & Lockers

Bathrooms, Science Lab & Locker Rooms

  • Restroom Rework (Items 97, 103, 115): Remove grab bars attached to toilet (Boys Rm near 5th grade); remove wooden urinal platform & set rim ≤17"; swap Girls Locker toilet for open-side flush ($8,074); recess Boys Restroom sinks obstructing 32"/36" path ($15,815).
  • Plumbing Protection (Items 46, 51): Install lavatory p-trap safety covers ($7,117) and replace Science Lab sink basins ($64,128, Mech-1).
  • Locker Room Benches (Item 101): Remove center benches and install wall-flush ADA benches (20" deep × 42" long × 17" high, Arch-1).
ADA Pillar 04 Site & Playground

Playground Surfacing & Exterior Routes

  • Accessible Playground Surfacing (Item 107): Replace swing wood chips and gravel playground paths with poured-in-place rubber or rubber tiles meeting ASTM F1487 & F1951-99 ($642,069 w/ markup, Civil-2).
  • Inclusive Play Equipment (Item 104): Add 2 ground-level play components and accessible swing seat/harness ($47,444, Civil-2).
  • Site Arrival & Entry Deck (Items 6, 91, 92): Rebuild sidewalks/curbs away from vehicle backing zones ($1,075,387, Civil-1), add detectable warning curb cuts & van-accessible signage ($47,444), and replace 1,100 SF entry wood deck ($115,973).
Section 05 Financial Breakdown, Discipline Exposure & Project Phasing
95 Documented Line Items · Exec. Summary Plan: $7,150,000

Mechanical Ventilation & Site Access Drive 75% of Documented Costs

While the Executive Summary establishes a $7,150,000 recommended 5-year capital expenditure plan, the 95 Attachment A line items preserved in the source excerpts total $4,316,603 in base construction cost and $13,832,879 with DEED’s full Alaska remodel markups across all horizons. Note that intermediate Attachment A rows (such as Item 30 for facility-wide interior door replacement) are elided in the source document excerpts; all figures below reflect exact sums of the 95 documented line items.

Capital Cost by Project Phase Grouping

Showing Cost with DEED Markup ($)

Discipline Exposure by Priority Tier

Stacked Cost with DEED Markup ($) across HLS, <5 yrs, and 5–15 yrs

Recommended Project Groupings (Section 4.3 Summary)

Phase Group Doc. Items Primary Scope Summary Base Cost Cost w/ Markup
Section 06 Attachment A Capital Improvement Line-Item Explorer
Click any row to expand full engineering & code notes

Searchable Schedule of Documented Capital Projects

Filter all 95 documented Attachment A items by discipline, priority tier, phase group, or keyword. Click any column header to sort or select a row to inspect report page numbers, expected useful life, and specific code citations.

Section 07 Administrative Record, Survey Team & Documentation
Governance & Provenance

Project Administration, Consultants & Archive Notes

Field Survey & Engineering Team

Role / Organization Personnel & Scope
Municipality of Skagway Borough
Client & Facility Liaison
P.O. Box 415, Skagway, AK 99840. Site survey accompanied by Tyson Ames, Skagway Director of Public Works, plus school maintenance staff.
CRW Engineering Group, Inc.
Prime Consultant (Proj. 22003.00)
Ryan Moyers, Christi Meyn, Austin Dabbs, Gavin Block, Ian Hofmann, Nick Choromanski — Structural, Mechanical, Electrical, and Civil assessments & DEED cost modeling.
Northwind Architects, LLC
Architectural Subconsultant
Dave Hurley, Shannon Crossley — Exterior enclosure, roof systems, interior finishes, specialties, and life-safety egress review.
Southeast Alaska Independent Living (SAIL)
ADA Consultation (Attachment B)
Bridget Thomson, Accessibility Specialist (bthomson@sailinc.org) — May 4, 2023 accessibility consultation under 2010 ADA Standards.
Jensen Yorba Wall, Inc.
As-Built Remodel Reference
Juneau, AK architectural/engineering firm responsible for the 2021–2022 Kitchen/Home Ec Remodel drawings (File 220002102, Nov 22, 2021).